Project Description

Client:   City of El Paso – Capital Improvements Department
Location:   Downtown El Paso
Surface Area:
Year Completed:   2014

Project consisted of the second phase of a new pedestrian pathway at the downtown chamber of commerce parking lot on the Durango street side.

More Details

Project consisted of removing the existing asphalt pavement and landscaping, new decorative sidewalks, new landscape & irrigation, new lighting, etc.
Original Contract Time: 200 calendar days (7 months)

Completion Time: 7 months (on time)
Major Subcontractors/Suppliers: Code Electric, Prime Irrigation & Landscape, Steel Specialties, Paso Del Norte Materials.