Project Description

Client:   City of El Paso – Capital Improvements Department
Location:   Downtown El Paso
Surface Area: 800 cubic yards
Year Completed:   2014

Different phases of project consisted of over 800 cubic yards of integral colored concrete using a 3600 PSI and TxDOT Class P mix with the City of El Paso.

Scope of Work

Project consisted of a new pedestrian pathway at the downtown Arts Plaza. Project consisted of removing the existing asphalt pavement, decorative brick pavers, planters, landscape and other amenities. The improvements included but were not limited to new decorative concrete pavement, repair of brick pavers, refurbishing of existing water feature, planters, landscape & irrigation, lighting and amenities.
Original Contract Time: 200 calendar days (7 months)
Completion Time: 7 months (on time)

Major Subcontractors/Suppliers: Code Electric, Prime Irrigation & Landscape, Steel Specialties, Paso Del Norte Materials.